Use Cases · Deliverables & Information Delivery
Delivered on time is half the equation.
The other half is whether it conforms.
Every deliverable tracked against the brief, the EIR and the programme, with a named owner, a live status and a forecast. "Delivered" means reviewed and conformant rather than received, and the record of what was promised survives as long as the liability does.
- Deliverables tracking
- EIR and brief conformance
- Information delivery status
- Ownership
Structural calculations packDue 12 Sep
One deliverable, four states.
Due
12 Sep, per the programme
Received
11 Sep, a day early
Log stops here
Reviewed
Against 9 information requirements
Conformant
7 of 9. Two schedules missing
Current practice
The tracker says delivered. The programme finds out later.
A deliverables schedule records dates and ticks. It cannot say whether what arrived satisfies the brief, whether anyone reviewed it, or who is accountable for the half that is missing. So a package lands, gets marked complete, and the gap surfaces weeks later in whatever depended on it.
The tracker is also only as current as the last person who updated it, which is usually the week of a report.
- Received and conformant are recorded as the same event
- Status is re-keyed by hand from minutes, so it lags the project
- Items shared between parties have no owner, so neither delivers them
- Slippage is visible once it has happened, not while it can still be absorbed
Information required for the stage gate
Structural calcs
Facade performance spec
Acoustic test report
Coordinated services model
Stage gate submission
- On plan
- Overrunning
- Knock-on
Tracked today across, for example
- MIDP and TIDP
- Design deliverable tracker
- RFI and technical query logs
- Contract deliverables
- Responsibility matrix
- BEP
- Deliverables to payment milestones
With Tektome
Due, owned, delivered, and actually conformant.
Every deliverable is held against the brief, the Employer's Information Requirements and the programme, with an owner attached and a status that reflects the review rather than the receipt. Forecasts are carried alongside due dates, so slippage appears while there is still time to act on it, and the position stands up in front of a client or an auditor.
Structural calculations packEIR §3.2 · 9 requirements
12 Sep
11 Sep
JRJ. Reeve Partial, 7 of 9Facade performance specificationBrief §7 · 14 requirements
29 Aug
19 Sep
?Unowned 21 days lateAcoustic test reportEIR §5.1 · 6 requirements
05 Sep
14 Sep
MKM. Kaur 9 days lateCoordinated services modelEIR §2.4 · 22 requirements
26 Sep
26 Sep
ATA. Toft Waiting on inputsFire strategy, revision 4Brief §4 · 11 requirements
22 Aug
21 Aug
SDS. Dahl Delivered, conformantStatus drawn from the latest issue and this week's minutes
1 – 5 of 46Facade performance specificationBrief §7 · due 29 Aug
Promised three times and delivered none of them. No owner has ever been assigned, which is why nobody was chased.
This week46 deliverables
28
Delivered and conformant
7
Received but not conformant
4
No owner assigned
Employer's Information Requirements
Rev 2 · 46 deliverables drawn
What you get
The outputs, and the evidence behind each one.
Tracked against the brief, the EIR and the programme
What is due, what has been received, what has been reviewed and what remains outstanding, measured against the documents that define the obligation rather than against a list somebody typed at the start of the job.
Why it mattersA deliverables list drifts from the brief the moment either changes. Holding them together is what keeps the tracker true.
Outstanding against plan · by week
- Outstanding, on plan
- Received but not conformant
Ownership visible, including where there is none
Every requirement and every deliverable carries a named owner. Where an item sits between two parties and neither has claimed it, that is stated rather than left to be discovered when it fails to arrive.
Why it mattersAn unowned deliverable is not a tracking problem. It is the one nobody is going to produce.
Owners · stage 4 information
Status that updates itself from the meeting
Minutes are read, and the actions, decisions and deliverable updates inside them are pulled straight into the tracker. Nobody re-keys a status the week before a report, and nothing said in a meeting quietly fails to reach the record.
Why it mattersMost trackers are accurate on the day they are updated and wrong every other day.
Minutes · week 36 progress meeting
As writtenItem 4.2. Facade spec now expected 19 Sep, delayed by the revised cladding build-up. MK confirmed the acoustic report will follow on 14 Sep. Client asked whether the gate date still holds.
- Updated
- Facade performance spec, forecast moved to 19 Sep
- Updated
- Acoustic test report, forecast 14 Sep, owner M. Kaur
- Raised
- Gate date at risk, flagged to the programme
Late and incomplete surfaced before it bites
A forecast sits alongside every due date, so a deliverable that is drifting is visible while there is still float to absorb it. Incompleteness counts as lateness here, because a package that arrives missing half its content has not really arrived.
Why it mattersThe window in which a slip is cheap to fix closes long before the slip shows up in a monthly report.
Due against forecast
Facade performance specification
Acoustic test report
Structural calculations pack
What was due, what was promised, what arrived
A linked record of the obligation and every promise made against it, with the meeting and the decision behind each one. If delivery is ever disputed, the sequence is already written down.
Why it mattersDelay claims turn on who promised what and when. That is a record you either kept at the time or reconstruct under pressure.
Facade performance specification
29 Aug
Due per the programme · original obligation
27 Aug
Promised for 05 Sep · week 34 meeting
04 Sep
Promised for 12 Sep · email, cladding build-up revised
11 Sep
Promised for 19 Sep · week 36 meeting
Three promises, no delivery, and every one of them recorded against the same obligation with its source attached.
Value
What the work produces, and the value it returns.
c.35%
of Gateway 2 applications turned back for missing information rather than bad design
Building Safety Regulator, reported statements
44.8%
of projects affected by inaccurate, incomplete or late design, the single largest causal cluster
HKA CRUX, 6th annual report, October 2023 · the design share has declined since
£10,000
per building per week cost of delay, so a 12 week slip is worth around £120,000
BSR Impact Assessment, cited by Centre for Cities · the size of the exposure, not a Tektome result
Why Tektome
A delivery log records arrival. A commitment rests on conformance.
Deliverables are tracked against the requirement register and the review status, not just a schedule of dates. That single difference is what lets "delivered" mean reviewed and conformant, which is the only version of delivered that a programme can safely be built on, and the only one that answers a delay claim years later.
| On this | A deliverables schedule | |
|---|---|---|
| What it records | That something arrived | Whether the obligation was met |
| What "delivered" means | Received and conformant are the same tick | Reviewed against the requirements, and conformant |
| How status is kept | Updated by hand, so it is current the week of a report and stale after | Drawn from minutes and issues as they happen |
| Ownership | Holds dates, not the requirements the deliverable has to satisfy | Every item carries an owner, and unowned items are named as such |
| When slippage shows | Once it has happened, not while it is forming | Forecasts sit beside due dates, so drift is visible while it is cheap |
Who this is relevant to
The date is the same. What a missed one costs is not.
A deliverable marked complete that does not satisfy the brief is not a tracking error. It is a programme commitment made on a tick, and the consequence lands well downstream of whoever entered it.
Legal and governance
General Counsel · Company SecretaryManaging Partner, Practice Director or Finance Director at design practices
A delivery record that holds up
What was due, what was promised, when it was re-promised and what finally arrived, each linked to the meeting or email behind it.
Insurance and risk
Whoever owns the PI programmeThe title varies by firm; the renewal obligation does not
Evidence against the information requirements
Deliverables measured against the EIR they exist to satisfy, not against a list that drifted from it months ago.
Information management
Information Manager · Head of Design ManagementBIM lead
Slippage while it is still cheap
A forecast beside every due date, updated from what was said in the meeting, so a drifting item surfaces while there is float to absorb it.
Delivery and packages
Project Manager · Package managerProgramme lead
Nothing unowned
A named owner on every deliverable, and an explicit flag on the ones sitting between two parties that neither has claimed.
In the project team
Architect · Engineer · BIM coordinator. See what a package still owes and what is blocked behind it, without re-keying a status into a fourth system.
Next step
Interested to learn more?
A 30-minute session: a deeper look at the platform, and a conversation about the information your firm owes and is owed. Nothing to set up, no project data needed.
- A deliverable opened against the requirements it owes
- A walkthrough on a project we have prepared
- Live Q&A with our engineering team
Book a 30-minute intro
Your request is in.
We'll be in touch shortly to find a time that works.